(کتاب فیدیک زرد)FIDIC Yellow Book2017
In the Contract the following words and expressions shall have the meanings stated, except where the context requires otherwise “Accepted Contract Amount” means the amount accepted in the Letter of Acceptance for the execution of the Works in …
Downloads
(کتاب فیدیک زرد)FIDIC Yellow Book2017
Typical Sequence of Principal Events During Contracts for Plant and Design-Build
The Time for Completion is to be stated (in the Contract Data) as a number of days, to which is added any
extensions of time under Sub-Clause 8.5
In order to indicate the sequence of events, the above diagram is based upon the example of the Contractor
failing to comply with Sub-Clause 8.2
The Defects Notification Period is to be stated (in the Contract Data) as a number of days, to which is added
any extensions under Sub-Clause 11.3
Depending on the type of Works, Tests after Completion may also be require